Ambitious targets for renewables and the transition to net zero are driving new infrastructure projects across the UK. However, there are several challenges to delivery which need to be addressed to enable the industry to scale up wind, solar, storage, and grid upgrades quickly enough to meet demand. Current projects are facing several constraints and bottlenecks, including delays in equipment delivery, ports infrastructure that needs upgraded, and a transmission grid that struggles to absorb new capacity.
Growing supply chain risks
Long lead items and logistics for large scale projects continue to be an issue and developers need to factor this in early to their projects. Transformers, cable, high‑voltage switchgear, turbine components, and inverters are manufactured in a small number of global facilities, and any disruption to factory outages, shipping delays, or export restrictions can push a project programme by months. Concerns