ARTICLE · 15 SEPTEMBER 2011

NOR Valid Despite Inclement Weather

The dispute concerned the interpretation of the laytime and demurrage terms under a CIF contract. Suek AG v Glencore International AG (2011).

United KingdomCorporate/Commercial Law
Barlow Lyde & Gilbert LLP
Barlow Lyde & Gilbert LLP

The dispute concerned the interpretation of the laytime and demurrage terms under a CIF contract. Suek AG v Glencore International AG (2011).

The Court had to determine whether, under a CIF contract of sale, the master had been entitled to give notice of readiness where firstly, the vessel had been unable to proceed with the discharge as the berth was occupied by another vessel when it reached the port and secondly, the weather was such that the vessel was prevented from reaching the berth in any event.

Clause 7.13 of the contract stipulated that "in case the berth was occupied on arrival, the vessel could tender notice of readiness at the usual waiting place ... whether in berth or not".

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.