Liquidated Damages: A Round Up

Fenwick Elliott LLP
Fenwick Elliott LLP
Contributor
Fenwick Elliott LLP

Fenwick Elliott LLP

Fenwick Elliott provides a comprehensive range of legal services on every aspect of the...

View firm profile
Explore more from Fenwick Elliott LLP

The recent TCC case of Eco World – Ballymore Embassy Gardens Company Limited v Dobler UK Limited and the Supreme Court case of Triple Point Technology, Inc v PTT Public Company Ltd...

United KingdomCorporate/Commercial Law

The recent TCC case of Eco World – Ballymore Embassy Gardens Company Limited v Dobler UK Limited1  and the Supreme Court case of Triple Point Technology, Inc v PTT Public Company Ltd2  provide much food for thought for those in the construction industry negotiating and interpreting liquidated damages provisions.

In this Insight,  we go "back to basics" on liquidated damages provisions, ask what lessons can be drawn from this recent case law, and highlight the points that those negotiating liquidated damages provisions may want to consider going forwards in light of these cases. 

So, what are liquidated damages?

As explained by Lord Leggatt in Triple Point: 

"A liquidated damages clause is a clause in a contract which stipulates what amount of money will be payable as damages  for loss caused by a breach of contract irrespective of what loss may actually be suffered if a breach of the relevant kind (typically, delay in performance of the contract)

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from