Contractual Advantage From Own Breach Not Allowed

In Extra MSA Services Cobham Ltd v Accor UK Economy Hotels Ltd [2011] EWHC 775 (CL) the claimant (a developer) made an application for a declaration of the High Court that the right to terminate an agreement for lease to construct a hotel (the defendant/tenant being a hotel chain) was not conditional on the proper performance by the claimant of its obligations under the agreement.

United KingdomCorporate/Commercial Law
Victoria Lloyd
Victoria Lloyd

Commercial Thinking

In Extra MSA Services Cobham Ltd v Accor UK Economy Hotels Ltd [2011] EWHC 775 (CL) the claimant (a developer) made an application for a declaration of the High Court that the right to terminate an agreement for lease to construct a hotel (the defendant/tenant being a hotel chain) was not conditional on the proper performance by the claimant of its obligations under the agreement.

The key provisions of the agreement were that: (i) the developer had to obtain "Requisite Consents" for the development to proceed; (ii) the developer had to use its reasonable endeavours to obtain the Requisite Consents by a specified longstop date; and (iii) a mutual right to terminate the agreement if the Requisite Consents were not obtained by the specified longstop date.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from