Time Bar Provisions Under FIDIC Contracts From A Turkish Law Perspective

As widely accepted in international construction practice, entitlement to a claim, such as time extension and additional payment, under construction contracts and, more specifically, under FIDIC-type contracts...

TurkeyReal Estate and Construction

As widely accepted in international construction practice, entitlement to a claim, such as time extension and additional payment, under construction contracts and, more specifically, under FIDIC-type contracts, time bars regulated under the contract constitute a condition precedent.  In other words, failure of the contractors to observe the time bar provisions and to serve the required notices within the period stipulated under the contract may lead to a cease of the contractors' entitlement to claims.

In that sense, FIDIC 99 Red Book Sub-Clause 20.1 reads as follows:

“If the Contractor considers himself to be entitled to any extension of the Time for Completion and/or any additional payment … the Contractor shall give notice to the Engineer, describing the event or circumstance giving rise to the claim. The notice shall be given as soon as practicable, and not later than 28 days after the Contractor became aware, or should have become aware, of the event or

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from