Turkey Updates Reimbursement Scheme For Investments In Electricity Transmission Assets

Moroglu Arseven
Moroglu Arseven
Contributor
Moroglu Arseven

Moroglu Arseven

Celebrating its 25th year, Moroğlu Arseven is an independent, full-service Turkish law firm...

View firm profile
Explore more from Moroglu Arseven

Turkey's Energy Market Regulatory Authority ("Authority") has updated the methodology for determining government reimbursements for investments in building new electricity transmission facilities, as well as lines to connect production and consumption facilities to the transmission system.

TurkeyEnergy and Natural Resources

Turkey's Energy Market Regulatory Authority ("Authority") has updated the methodology for determining government reimbursements for investments in building new electricity transmission facilities, as well as lines to connect production and consumption facilities to the transmission system.

The methodology is used to calculate reimbursements for such construction where:

  • The Turkish Electricity Transmission Corporation ("TEİAŞ") had insufficient funds, or
  • TEİAŞ failed to make an investment plan in a timely manner and new electricity transmission facilities and lines were required for electricity production and consumption facilities to enable connection to the electricity transmission system.