"The country needs to make large
investments to propel economic activity. ... Current investment
levels are insufficient and maintenance programmes are lagging. ...
Priority should be given to infrastructure programmes that
contribute to regional integration."
(p160 of the National Development Plan)
Notwithstanding that the construction industry remains in a
slump, that tender activity continues to decline, and that capital
expenditure, market capitalisation and net profit relative to the
larger South Africa contractors is substantially down, Government
would appear intent on pursuing the expansion of infrastructure and
power generation.
This is borne out by several infrastructure projects which are
currently in the planning or implementation stages, most notably
Phase 2 of the Lesotho Highlands Water Project, Renewable Energy
Independent Power Producer Procurement Programme (REIPPP
Programme), and the Gautrain Extension Project.