Effect On Demand Guarantees: Clause 4.2.2 In FIDIC Red 2017

In the FIDIC suite of contracts, the contractor is ordinarily required to obtain a performance security within 28 days of receiving the Letter of Acceptance.

South AfricaReal Estate and Construction

In the FIDIC suite of contracts, the contractor is ordinarily required to obtain a performance security within 28 days of receiving the Letter of Acceptance. In terms of the 2017 edition of the FIDIC Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer (more commonly known as the FIDIC "Red Book"), clause 4.2 is the key clause dealing with the contractor's performance security.

The 'performance security' usually takes the form of a performance guarantee, also known as a performance bond, and is arguably the most common type of guarantee in the construction industry. The function of this particular guarantee is to safeguard the employer against non-performance, late performance or insufficient performance by the contractor.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from