The Singapore Appellate Court has re-confirmed that delay
liquidated damages stop accruing on the date a contract is
terminated.
This is an important decision for parties to Singapore
law-governed construction agreements. The established Singapore
position, which allows an employer to rely on liquidated damages
provisions even when the contract is terminated, was called into
question following the decision in Triple Point Technology Inc v PTT Public Co
Ltd [2019] EWCA Civ 230. While that decision was
overturned by the UK Supreme Court (see
our analysis here), the Supreme Court did not explicitly affirm
the correctness of the Singapore approach. Diamond Glass
now confirms that the positions under Singapore law and English law
are aligned.