No Claim For Liquidated Damages In The Absence Of An Extension Of Time ("EOT") Clause

In Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd [2019] SGHC 4, the Singapore High Court dealt with the issue of delay caused by an employer's act of prevention, particularly in the context of a construction contract ...

SingaporeReal Estate and Construction

In Crescendas Bionics Pte Ltd v Jurong Primewide Pte Ltd [2019] SGHC 4, the Singapore High Court ("SGHC") dealt with the issue of delay caused by an employer's act of prevention, particularly in the context of a construction contract that did not contain an extension of time ("EOT") clause. In this case, the plaintiff property developer employed the defendant contractor for the construction of a business park. The signed Letter of Intent, which both parties agreed to be legally binding on them, contained a clause specifying the date of completion and a liquidated damages clause but did not include an EOT clause. When the project was certified to be completed after the specified completion date, the plaintiff sued the defendant for, inter alia, liquidated damages for the delay in completion. The defendant, in its defence, argued that since the plaintiff was responsible for the delays and there was no EOT clause, time was at-large and it only needed to complete its

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from