Liquidated Damages Not Recoverable Where Contract Terminated Prior To Completion

In Triple Point Technology, Inc v PTT Public Company Ltd [2019] EWCA Civ 230, the UK Court of Appeal addressed the question of whether an employer was entitled to liquidated damages where the contract ...

SingaporeReal Estate and Construction

In Triple Point Technology, Inc v PTT Public Company Ltd [2019] EWCA Civ 230, the UK Court of Appeal ("EWCA") addressed the question of whether an employer was entitled to liquidated damages where the contract had been terminated prior to the contractor completing the work.

PTT had engaged Triple Point to supply a new commodity trading software system. Payment was by milestone or specified dates. The project was to be completed in stages with a completion date for each stage. Triple Point's work progress was slow. The first two stages of phase 1 were to be completed by 31 October 2013 but were completed late on 19 March 2014. That only the first two stages of phase 1 were completed was not disputed by Triple Point. On 27 May 2014, Triple Point suspended work and left the site. The last stage completion date was 11 June 2014. On 15 February 2015, PTT terminated the contract.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from