Implying Terms Of Due Diligence And When Time Is Of The Essence In Construction Contracts

A case study of CAA Technologies Pte Ltd v Newcon Builders Pte Ltd [2016] SGHC 246.

SingaporeReal Estate and Construction

A case study of CAA Technologies Pte Ltd v Newcon Builders Pte Ltd [2016] SGHC 246



Overview

In CAA Technologies Pte Ltd v Newcon Builders Pte Ltd [2016] SGHC 246, the Singapore High Court held that it could be appropriate to imply a term requiring contractors to perform their obligations with due diligence and expedition, and with respect to that, a term making time of the essence could be implied. The court also held that if, after the signing of a letter of intent, a party does not unequivocally signify its acceptance to a subsequent contract, that subsequent contract could not form part of the parties' contract.

This update takes a closer look at the decision.

Background

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.