Executive Summary
It is commonplace in our local building and construction market
for the same parties to enter into multiple contracts for different
projects. However, what happens if a main contractor has valid
backcharges under Project A and wants to apply these to reduce
payment for certified work done on Project B? Will the backcharges
be considered valid set-offs for the purposes of adjudication under
the Building and Construction Industry Security of Payment Act (Cap
30B, 2006 Rev Ed) (the SOP Act)?
Recently, the Singapore High Court (the Court) in Hua Rong
Engineering Pte Ltd v Civil Tech Pte Ltd, [2017] SGHC 179
decided that one cannot do so.
The Court was of the view that permitting parties to introduce
any contracts they wanted to in an adjudication determination under
the SOP Act would open the floodgates to unchecked expansion of the
scope of materials which must be dealt with. More crucially, this
may even lead to unmanageable complexity, which will