Share on LinkedInShare on LinkedIn

ARTICLE · 06 MARCH 2025

Clarifying The Role Of Intention In Awarding Cost Of Cure Damages: Insights From Terrenus Energy SL2 Pte Ltd V Attika Interior + MEP Pte Ltd

The recent decision in Terrenus Energy SL2 Pte Ltd v Attika Interior + MEP Pte Ltd [2025] SGHC(A) 4 by the Appellate Division of the High Court of Singapore provides significant insights...

SingaporeReal Estate and Construction

Introduction

The recent decision in Terrenus Energy SL2 Pte Ltd v Attika Interior + MEP Pte Ltd [2025] SGHC(A) 4 by the Appellate Division of the High Court of Singapore provides significant insights into the principles governing the award of cost of cure damages in construction contracts. This case addresses the contentious issue of whether a claimant's intention to incur the cost of cure is a necessary prerequisite for claiming such damages. The court's reasoning and conclusions offer clarity and guidance on this area of law.

Background

The dispute arose from a construction project for a solar power generation facility, where Terrenus Energy SL2 Pte Ltd (Terrenus) engaged Attika Interior + MEP Pte Ltd (Attika) as the main contractor. Terrenus claimed damages for defective works, particularly the improper installation of PEG Rods, and sought liquidated and general damages for delays. Attika counterclaimed for the unpaid balance of the contract sum. The lower

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from