In Global Switch (Property) Singapore Pte Ltd v Arup
Singapore Pte Ltd [2019] SGHC 122, one of the main issues that
the Singapore High Court ("HC")
considered was whether 'fitness for purpose' was an implied
term in a data centre construction contract.
Sometime around 2008, the plaintiff embarked on its project to
construct an extension (the "Extension")
to its existing data centre facility and engaged the defendant as
its mechanical and electrical
("M&E") consultant. In May 2013, the
plaintiff complained, inter alia, that the utility mains
power supply experienced disturbances, which in turn resulted in
overloading of the back-up systems and failure of the
plaintiff's tenants' IT equipment. The plaintiff then sued
the defendant for breach of contract. Particularly, the plaintiff
claimed that there was an implied term in the contract that the
defendant needed to ensure that its designs for the M&E systems
would "meet the needs of the operation of a data centre