A party can terminate a contract pursuant to an agreed contractual mechanism.

SingaporeCorporate/Commercial Law

A party can terminate a contract pursuant to an agreed contractual mechanism. However, you can also do so by accepting the other party's repudiatory breach. So, what amounts to a repudiatory breach? Will it amount to a repudiatory breach if you insist the other party complies with conditions that are not part of the contract? The recent case of Sunrise Industries (India) Ltd v. PT. OKI Pulp & Paper Mills & Anor [2023] SGHC 3 ("Sunrise v OKI") addresses this.

Brief facts. In Sunrise v OKI, the plaintiff, Sunrise Industries (India) Ltd ("Sunrise") was engaged by the first defendant, PT. OKI Pulp & Paper Mills ("OKI") to supply and install pipes, fittings and manholes for a pump mill owned by OKI in Indonesia. This was done via two separate contracts: a supply contract for Sunrise to supply OKI with various goods (the "Supply Contract"), and a separate contract (the "Installation Contract") for Sunrise to install those goods in the mill.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from