Application Of SOPA Timelines Notwithstanding Termination Of Contract

In CHL Construction Pte Ltd v Yangguang Group Pte Ltd [2019] SGHC 62, the Singapore High Court ("SGHC") considered whether, with respect to SOPA claims, contractual provisions relating to SOPA timelines survive...

SingaporeCorporate/Commercial Law

In CHL Construction Pte Ltd v Yangguang Group Pte Ltd [2019] SGHC 62, the Singapore High Court ("SGHC") considered whether, with respect to SOPA claims, contractual provisions relating to SOPA timelines survive termination of the contract.

On 9 July 2018, the defendant subcontractor completed the works for the plaintiff main contractor, and a Certificate of Substantial Completion ("CSC") was received the next day. Shortly after, the parties' contract was terminated. The defendant then submitted its penultimate payment claim on 30 August 2018 for works done until completion and for half of the retention monies. However, it was stipulated in Clause 37 of the parties' contract that the defendant had to withhold its penultimate claim "until three months after the CSC has been received by" the plaintiff. The dispute therefore centred around whether the penultimate payment claim was served prematurely, in contravention of s 10(2)(a) SOPA.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from