Securing The Necessary Grid Capacity

Securing grid capacity is a critical legal and operational challenge for data centre developers in Norway. This article examines the evolving regulatory framework governing how grid companies allocate capacity, the stringent maturity requirements projects must meet to secure and maintain their position in capacity queues, and the strategic implications of Norway's shift from a "first come, first served" to a "first mature project come, first served" principle.

NorwayEnergy and Natural Resources
Solveig Lingaas
Solveig Lingaas
Frida Hammervik
Frida Hammervik

In this article, we turn to a question that is often decisive for whether a data centre project can be realised at all: how does a data centre operator secure the necessary grid capacity, and if placed in a capacity queue, what does it take to maintain and progress your place?

Securing sufficient grid capacity is a legal precondition for establishing a data centre. Under Section 3-4 of the Energy Act, grid companies holding an installation license are, upon request, obliged to connect new customers, or to accommodate increased consumption by existing customers. Under section 3-3, a grid company holding an area license is obliged to invest in new grid infrastructure to connect new grid customers or to allow an increased power consumption. Grid capacity may therefore, as a general rule, be allocated to everyone. 

How do grid companies allocate grid capacity?

However, as a starting point, grid connection requires capacity to be available in the grid – the connection must be operationally sound. Where it is operationally sound to connect the customer, a mature customer may reserve the necessary grid capacity. Where a connection is not operationally sound, however, the mature request is placed in a capacity queue pending grid reinforcement or the release of capacity by other means.

When issuing capacity reservations and operating the queue, the grid company must act in a neutral and non-discriminatory manner. This requirement was previously given effect through a “first come, first served” principle. 

However, the increased scarcity of grid capacity in Norway in recent years has put that principle under pressure. Since 1 January 2025, the applicable principle has been “first mature project come, first served”. In essence, all new capacity requests must be assessed by the grid company, and only mature projects are granted a capacity reservation or placed in the capacity queue. 

When is a project “mature”?

It is the responsibility of the individual grid company to establish the relevant criteria for maturity, and consequently to determine grid capacity allocation among potential customers. Pursuant to section 3-4 of the regulations on grid regulation and the energy market (the NEM regulations), the assessment must, as a minimum, be based on seven criteria: 

  1. project description;
  2. actual capacity need;
  3. timing of use of the capacity;
  4. a binding progress plan;
  5. the status of relevant permits and agreements;
  6. location; and
  7. a financing plan.

In practice, this means that the applicant must document a project-specific power requirement, clarified site access, a realistic financing plan and a progress plan with concrete milestones up to the point of connection. In addition, the relevant grid company may adopt additional requirements, provided they are practised in a neutral and non-discriminatory manner for all applicants.

While some grid companies have developed their own maturity assessment requirements, most grid companies now rely on the industry organisation Renewables Norway’s best practices. For capacity requests of 100 MW or more, the Norwegian TSO Statnett shall perform the maturity assessment. They have developed stricter requirements on top of Renewables Norway’s best practice document. The most important difference between these documents is Statnett’s requirement that the project site shall be zoned for the right purpose. Read more about these requirements in our article. 

What are the risks of delayed grid access?

Several applicants often compete for the same grid capacity. As a result, ensuring project maturity at an early stage may be critical.

A project enters the queue by satisfying the grid company’s maturity criteria described above. The position in the queue is determined by the date on which sufficient documentation is delivered, and the place in the capacity queue is only secured once a complete application is submitted. This makes timing essential; if a project is placed behind one or several large-scale projects, this may result in significant delays in the allocation of capacity, with corresponding consequences for the intended project timeline.

How is reserved capacity or a place in the capacity queue retained?

Neither a reservation nor a place in the queue is a permanent right. To retain either, the applicant must maintain sufficient progress for the project, in accordance with the project plan submitted to the grid company.

The grid companies regularly request reporting on whether the maturity criteria continue to be met, and must continuously assess whether the project is progressing adequately. Where there are material deviations or changes for which the applicant is responsible or bears the risk, the grid company is obligated to withdraw the queue position, and all or part of the reserved capacity. An applicant who loses its reservation or place in the queue must, in practice, restart the process.

Both Renewables Norway’s best practices and Statnett’s new maturity requirements (both applicable since 1 July 2026) stipulate that the project should, as a starting point, be operational within six years from the date it was approved as mature. Exceptions apply in certain scenarios, such as innovation and pilot projects and where the grid connection is dependent on grid reinforcements which take more time. 

What does this mean for prospective data centre developers?

Maturity requirements must be met at an early stage of the project. It is not enough to point to intentions regarding financing or preliminary zoning plans. In practice, work on zoning, land acquisition and financing documentation should begin early, and will be continuous work. These regulations, and the grid companies’ practising of them, are still evolving and the effects for your projects should be monitored closely. 