Important Announcements Today Related To The Natural Gas Market In Mexico

The First Annual Revision to the Five-year Plan of Expansion of the Integrated Natural Gas Transportation System 2015-2019 (the "Plan") was released today July 25, 2016.

MexicoEnergy and Natural Resources

The First Annual Revision to theFive-year Plan of Expansion of the Integrated Natural Gas Transportation System 2015-2019 (the "Plan") was released today July 25, 2016. Seven projects were confirmed and kept in the Plan as follows:

San Isidro-Samalayuca pipeline
Samalayuca-Sasabe pipeline
Tuxpan-Tula pipeline
Tula-Villa de Reyes pipeline
Villa de Reyes-Guadalajara pipeline
La Laguna-Aguascalientes pipeline
South Texas-Tuxpan pipeline

Six projects were either removed, rescheduled or modified from the original Plan as follows:

  1. Colombia-Escobedo pipeline (removed from the Plan since the "Nueva Era" pipeline project of Midstream de Mexico will attend the demand along its route)