Riżorsi Agrikoli Malta (“RAM”) has launched a pre-qualification process for the award of a major concession concerning the development and operation of a National Farm Waste Treatment Facility.
The project, issued under reference RAM/001/2026, will be delivered through a design, build, finance, operate and transfer (“DBFOT”) model. The concessionaire will be responsible for financing and constructing the facility, operating and maintaining it for 25 years, and ultimately transferring it back.
The estimated value of the concession is €511 million excluding VAT. This represents the estimated turnover over the 25-year operating period, rather than the facility’s construction cost. Indicative capital expenditure is expected to be between €70 million and €90 million, with annual operating expenditure estimated at between €8 million and €12 million.