Share on LinkedInShare on LinkedIn

ARTICLE · 12 JUNE 2024

Italian Court Decision On Renewables: Final Measure Must Be Adopted Within The Deadlines Set By The Consolidated Environment Act

Osborne Clarke LLP
Osborne Clarke LLP
Contributor
Osborne Clarke LLP

Osborne Clarke LLP

About us Osborne Clarke is an international, full service law firm 1, headquartered in London. We...

View firm profile
Explore more from Osborne Clarke LLP

The Lazio Regional Administrative Court, in judgment no. 1503 of 24 May 2024, has clarified that the public administration is obliged to adopt the final express measure, authorising...

ItalyEnergy and Natural Resources

Case may be of assistance to businesses struggling with administrative delay in approving renewable energy source plants

The Lazio Regional Administrative Court, in judgment no. 1503 of 24 May 2024, has clarified that the public administration is obliged to adopt the final express measure, authorising – or otherwise - the renewable energy source plants (RES), of the proceedings in compliance with the peremptory terms provided for by the Consolidated Environmental Law Act.

Failing that, the private claimants concerned may bring an action pursuant to articles 31 and 117 of the Code of Public Procurement to obtain an order that the public administration (PA) issue the final measure within a time limit to be set.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from