The final FER X Decree entered into force on August 7, 2026, introducing Italy’s long-term support framework for renewable energy technologies with generation costs close to market competitiveness. The regime covers solar photovoltaic (PV), onshore wind, hydropower, and sewage-gas projects until December 31, 2030, supporting up to 37.15 GW of capacity: 27.15 GW through indicative auction volumes and up to 10 GW through direct access for plants up to 1 MW.
The decree is in force, but the Ministry of Environment and Energy Security (MASE), Regulatory Authority for Energy, Networks and Environment (ARERA), and the Energy Services Manager (GSE) must still adopt rules on auction volumes, strike prices for smaller plants, preliminary qualification, operating rules, balancing, and deemed production.