Energy Update: Sharing Maximum Export Capacity At Electricity Grid Connection Points

The Commission for Regulation of Utilities (“CRU“) has issued a decision to allow a single contracted Maximum Export Capacity (“MEC”)...

IrelandEnergy and Natural Resources

The Commission for Regulation of Utilities (“CRU“) has issued a decision to allow a single contracted Maximum Export Capacity (“MEC”) at a connection point to be dynamically shared between multiple generation and/or storage units behind the connection point.

The decision is available here: Decision on Sharing Maximum Export Capacity (MEC) behind a Single Connection Point. It follows the CRU’s 2025 consultation, which we looked at here: Potential Impact of Hybrid Connection Proposal on Priority Dispatch.

Scope

The decision applies to “Hybrid Co-located Projects”. The CRU defines these as projects that combine multiple forms of generation and/or storage technologies behind a single defined connection point to the distribution or transmission network where the generation units for the different technologies are individually sub-metered and registered, and operate independently of one another for market, settlement, and dispatch purposes.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from