ARTICLE · 29 JULY 2026

Legal Update – Gujarat’s Bets On Data Center Opportunity: Decoding The Viksit Gujarat Data Center Policy

Gujarat has unveiled a comprehensive policy framework designed to transform the state into India's premier data center destination, offering unprecedented fiscal incentives including power tariff subsidies, capital grants, and tax exemptions worth up to 75% of eligible investments. The policy targets 7.5 GW of aggregate data center capacity with enhanced operational support and mandates renewable energy integration, positioning Gujarat to compete with global data center hubs.

IndiaStrategy

On July 9, 2026, the State Government of Gujarat has launched the Viksit Gujarat Data Center Policy 2026–2029 (“Policy”), a dedicated sectoral framework aimed at establishing the State as a hub for hyperscale, colocation and artificial-optimised data centers, replacing the smaller-scale incentives under the Gujarat Information Technology and Information Technology Enabled Policy 2022–2027. The Policy introduces a substantially enhanced incentive package (both financial and non-financial in nature) and operational support provisions for allied components in data center infrastructure.

S. No. Basis Particulars
1. Fiscal Incentives
  • Capital Subsidy – Capital subsidy of 2.5% on Eligible Fixed Capital Investment (“EFCI”) made within the eligible investment period under this Policy for Dholera region. The eligible entity may submit claim(s) for such incentive up to a period of 10 years from the date of grant of in-principal approval under this Policy. The EFCI considered

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from