Further the Court also directed the State Governments and the concerned Union territories to set up ‘common effluent treatment plants' mandatorily within a period of three years.

IndiaEnvironment

The Paryavaran Suraksha Samiti (PSS) approached the Apex Court with a writ petition in the nature of mandamus (command) in 2012, seeking action from the Union Government as well as States and Union Territories towards prevention of pollution by ensuring that no industry that requires a "consent to operate" from a Pollution Control Board, would be permitted to function, unless it had a functional effluent treatment plant, capable of meeting the prescribed norms for removing the pollutants from the effluent, before it is discharged.1.

On 22nd February, 2017 Supreme Court passed its judgement in this regard laying down a mandate for industries to have 'functional' primary effluent treatment plant, within three months from the date of passing of judgement. Further the Court also directed the State Governments and the concerned Union territories to set up 'common effluent treatment plants' mandatorily within a period of three years.