Share on LinkedInShare on LinkedIn

ARTICLE · 16 MARCH 2021

Market Intelligence Thought Leadership Award Winner

EIA Notification 2006 Amended To Make ‘No Increase In Pollution Load' The Criteria For Seeking Exemption From Environmental Clearance For Changes In Existing Projects

Shardul Amarchand Mangaldas & Co
Shardul Amarchand Mangaldas & Co
Contributor
Shardul Amarchand Mangaldas & Co

Shardul Amarchand Mangaldas & Co

Founded on a century of legal achievements, Shardul Amarchand Mangaldas & Co (SAM & Co) was born...

View firm profile
Explore more from Shardul Amarchand Mangaldas & Co

Environmental Impact Assessment ("EIA") Notification was promulgated by the Ministry of Environment, Forest and Climate Change ("MoEFCC")...

IndiaEnvironment

Introduction

Environmental Impact Assessment ("EIA") Notification was promulgated by the Ministry of Environment, Forest and Climate Change ("MoEFCC") in 2006 to scrutinize all relevant information about a project or activity in order to assess (and accordingly mitigate) its potential adverse impacts on the ecology of a region. As it seeks to uphold the 'precautionary principle' of environmental governance, it strictly mandates that following activities: construction of new projects or activities listed in its Schedule; the expansion or modernisation of existing projects or activities listed in its Schedule with increase in production capacity through the change in process and/or technology; or change in the product mix in existing manufacturing units beyond the specified range, shall be undertaken in any part of India only after obtaining prior environmental clearance ("EC") from the appropriate authorities.1

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from