To prevent the spread of the Covid-19 pandemic, the Government
of India, vide its order dated March 24, 2020, under Section
10(2)(l) of the Disaster Management Act, 2005, ordered a lockdown
of the entire country except the essential services for a period of
21 days effective from March 25, 2020 which has now been extended
to May 17, 2020 following two extensions.
The GOI has also issued guidelines in furtherance to its order
dated 24.03.2020 to contain the spread of Covid-19. Further, any
violation of these guidelines would attract action under Section 51
to 60 of the Disaster Management Act, 2005 and Section 188 of the
IPC.
This Covid-19 pandemic is a force majeure event and in contracts
where there is no clause of force majeure event, Section 56 of the
Indian Contract Act, 1872, can be triggered to claim the
impossibility of performance. However, the question is whether this
lockdown order due to Covid-19 can amount to Change in Law? As for
the EPC agreements