A single-judge bench of the Hon'ble High Court of Delhi (High Court), in its judgment, MEP Infrastructure Developers Limited v South Delhi Municipal Corporation & Ors.

IndiaCoronavirus (COVID-19)

A single-judge bench of the Hon'ble High Court of Delhi (High Court), in its judgment, MEP Infrastructure Developers Limited v South Delhi Municipal Corporation & Ors. dated 12 June 2020, held that a force majeure clause instantly comes into effect once it has been acknowledged by the other party. Accordingly, in such circumstances, the need to explicitly invoke the force majeure clause does not arise.

BRIEF FACTS

The petitioner, a contractor of a highway development project, was liable to pay revenue to the respondent for being allowed to collect toll on a concerned stretch of road as per the terms of a Toll Collection Contract (Contract). The petitioner defaulted in making the weekly payment under the terms of the Contract. Consequently, the payment was directed to be made to the respondent in three equal monthly instalments vide an order dated 26 November 2019. Thereafter, vide an order dated 2 March 2020, the High Court, reaffirming its earlier order, directed

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this document does not necessarily reflect the views / position of Khaitan & Co but remain solely those of the author(s). For any further queries or follow up, please contact Khaitan & Co at [email protected].

See more popular content from