A single-judge bench of the Hon'ble High Court of Delhi
(High Court), in its judgment, MEP Infrastructure Developers
Limited v South Delhi Municipal Corporation & Ors. dated
12 June 2020, held that a force majeure clause instantly
comes into effect once it has been acknowledged by the other party.
Accordingly, in such circumstances, the need to explicitly invoke
the force majeure clause does not arise.
BRIEF FACTS
The petitioner, a contractor of a highway development project,
was liable to pay revenue to the respondent for being allowed to
collect toll on a concerned stretch of road as per the terms of a
Toll Collection Contract (Contract). The petitioner defaulted in
making the weekly payment under the terms of the Contract.
Consequently, the payment was directed to be made to the respondent
in three equal monthly instalments vide an order dated 26
November 2019. Thereafter, vide an order dated 2 March
2020, the High Court, reaffirming its earlier order, directed