Liquidated Damages On Work Never Completed

PTT would however be entitled to recover damages at large, based on ordinary principles and subject to proof by PTT.

Hong KongReal Estate and Construction

The English Court of Appeal recently considered what should happen when a contractor, through its own fault, never delivers any completed work, despite having contracted to do so by a particular date. In Triple Point Technology, Inc v PTT Public Company Ltd [2019] EWCA Civ 230, 5th March 2019, the Court of Appeal had to choose between three different approaches set out in previous case law, but in which consistency seemed notoriously absent.

A software solution?

PTT, a commodities trader based in Thailand, entered into a bespoke contact to procure a software system from Triple Point, a software systems supplier. The contract included milestone payments and specific dates for payment.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from