Summary
In Sze Fung Engineering Limited v Trevi Construction Company
Limited [2025] HKCA 2781, the Hong Kong Court of
Appeal ("CA") ruled that the "back to back"
wording in that case was not a "pay when paid" clause,
but governed only the timing of payment.
Background
These proceedings arose out of a construction project to build a
new combined gas turbine unit. The plaintiff was a
sub-sub-contractor ("SSC") and the defendant was the
sub-contractor ("SC"). It was common ground between the
parties that the quotation submitted by the SSC to the SC formed
part of the sub-sub-contract between the parties.
Item 18 of the quotation provided that:
"Payment is based on 'back to back'
principle and to be released to [SCC] within 3 days upon receipt of
the same from Client."