Damage, Defects And Delay – The Interplay Between Insurance And Construction Claims

Herbert Smith Freehills Kramer LLP
Herbert Smith Freehills Kramer LLP
Contributor
Herbert Smith Freehills Kramer LLP

Herbert Smith Freehills Kramer LLP

We have one of the largest Southeast Asia international law practices, working across the region...

View firm profile
Explore more from Herbert Smith Freehills Kramer LLP

When disputes arise in the context of a construction project (which they commonly do) and the principal seeks recourse for damage and delays, a complex interplay can arise between claims between principal and contractor, and claims with insurers.

GlobalReal Estate and Construction

When disputes arise in the context of a construction project (which they commonly do) and the principal seeks recourse for damage and delays, a complex interplay can arise between claims between principal and contractor, and claims with insurers. Focusing on one to the exclusion of the other can inadvertently create a gap in recovery, leaving money 'on the table'.

Unfortunately, this is a situation that arises all too often, particularly where the respective claims are handled by different teams within their organisation, without coordination. Developing a holistic recovery strategy, addressing claims against both the contractor and insurers, allows principals to assess the relative strengths and priority of the claims, make informed decisions when conducting both claims, and maximise overall recovery.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from