In Carillion Construction Limited v Emcor Engineering Limited and Others [2017] EWCA Civ 65 Carillion contended that the wording of a particular clause and commercial common sense warranted a move away from ...

GlobalReal Estate and Construction

JANUARY

UK

In Carillion Construction Limited v Emcor Engineering Limited and Others [2017] EWCA Civ 65 Carillion contended that the wording of a particular clause and commercial common sense warranted a move away from the traditional approach of awarding contiguous EOTs, allowing it instead to grant non-contiguous EOTs to its subcontractor.

The case involved a 182 day delay for which Carillion blamed Emcor (in part). However, events had also occurred post-completion that would otherwise entitle Emcor to an EOT. Carillion argued that any EOT should be added non-contiguously. That is, not run continuously from the end of the current period for completion but be fixed at a later date to accurately reflect the period for which Emcor had been delayed but also take into account the period for which it was in culpable delay. Per this approach Emcor would bear the responsibility for the delay that it caused and be liable to Carillion for damages for the period between

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from