ECJ Partially Upholds Appeals Against General Court Judgment In Gas Insulated Switchgear Cartel Case

Van Bael & Bellis
Van Bael & Bellis
Contributor
Van Bael & Bellis

Van Bael & Bellis

Van Bael & Bellis is a leading independent law firm headquartered in Brussels with offices in...

View firm profile
Explore more from Van Bael & Bellis

The European Court of Justice handed down two judgments partially upholding appeals brought by the European Commission.

European UnionAntitrust/Competition Law

On 10 April 2014, the European Court of Justice (ECJ) handed down two judgments partially upholding appeals brought by the European Commission, Siemens Transmission & Distribution Ltd (Reyrolle), Siemens Transmission & Distribution SA (SEHV), Nova Magrini Galileo SpA (Magrini) and others, on the one hand, and by Areva SA (Areva) and Alstom SA (Alstom), on the other hand. The appeals had been brought against the General Court's (GC) judgments of 3 March 2011 which had partially annulled the European Commission's decision in the gas insulated switchgear cartel case.

On 24 January 2007, the Commission imposed fines totalling € 750.7 million on eleven producers of gas insulated switchgear for their participation in a cartel consisting of, among others, bid-rigging, price-fixing and market-allocation during two consecutive infringement periods (1988-1999 and 2002-2004) (see VBB on Competition Law, Volume 2007, No. 2, available at www.vbb.com).