Late delivery of an off-plan home can leave a buyer paying rent after committing substantial funds to the purchase. Compensation may be available for the developer’s breach, but a missed deadline does not always entitle the buyer to end the agreement. An unjustified termination can itself put the buyer in breach.
For purchases in the areas controlled by the Republic of Cyprus, the sale agreement defines the developer’s delivery obligation. Subsequent correspondence may record an agreement to extend time or change the works, altering what the buyer can enforce.
What was the developer required to deliver
Construction completion, possession and transfer of title are different events. An agreement may provide for the home to be handed over before a separate title deed is issued. The absence of that deed does not, by itself, establish a breach of the delivery obligation. Handing over keys while essential works remain unfinished does not necessarily fulfil the delivery obligation.