ARTICLE · 11 NOVEMBER 2019

Understanding The CCDC 30 Integrated Project Delivery Contract: Waivers And Releases

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP ("Miller Thomson") is a national business law firm with approximately 500...

View firm profile
Explore more from Miller Thomson

In our last article, we provided an overview of Building Information Modeling ("BIM") and the new Integrated Project Delivery Contract ("IPD Contract") needed to realize its full potential.

CanadaReal Estate and Construction

In our last article, we provided an overview of Building Information Modeling ("BIM") and the new Integrated Project Delivery Contract ("IPD Contract") needed to realize its full potential. This article will take a closer look at the differences between the release and waiver provisions of the traditional CCDC Contracts and those found within the new CCDC 30 – IPD Contract.

The first difference with the IPD Contract waiver and release provisions is the number of parties that are bound by them. The driving idea behind IPD Contracts is to include all major parties to the project so that risks and rewards can be shared. At a minimum, this means including the contractor, the client and the advisor. However, the express intention is to include any other main party. Such a reach has the effect of transforming the IPD Contract into a true partnership.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from