The New Construction Act: Summary And Timelines Of Major Changes

Overview: This Part sets out short timelines for the payment of contractor and subcontractor invoices.

CanadaReal Estate and Construction

Part I.1 – Prompt Payment

Overview: This Part sets out short timelines for the payment of contractor and subcontractor invoices. The payer is required to make payments in accordance with the timelines, unless it provides a notice of non-payment. Amounts not paid in accordance with the timelines will accrue interest at a specified rate. The prompt payment regime applies to both private and public contracts.

A – Payment Trigger

The trigger for payment is the delivery of a proper invoice to the owner.  It is provided on a monthly basis, unless the contract provides otherwise.  A contract cannot make the giving of a proper invoice contingent upon payment certification or the prior approval of the invoice by the owner.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from