The first tranche of revisions to the Construction Act (the "Act") came into force on July 1, 2018. Some of the most anticipated changes were the extensions of the lien timelines.

CanadaReal Estate and Construction

The first tranche of revisions to the Construction Act (the “Act”) came into force on July 1, 2018. Some of the most anticipated changes were the extensions of the lien timelines. For subcontractors, the time to preserve the lien by registering a claim for lien was increased from 45 days to 60 days, and the time to perfect by commencing an action was increased from 45 days to 90 days.

But there is a significant catch in the form of the three transition provisions in the Act.

The transition provisions say that in certain circumstances, the old timelines will apply, even if a subcontract was entered into after July 1, 2018.

Two of the transition provisions are based on the circumstances surrounding the contract between the owner and the contractor (the “contract” in the Act). The third transition provision is based on whether the premises is subject to a leasehold interest. If any one of the three circumstances exist, then the old timelines apply.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be ought about your specific circumstances.

See more popular content from