The first tranche of revisions to the Construction Act
(the “Act”) came into force on July 1, 2018. Some of
the most anticipated changes were the extensions of the lien
timelines. For subcontractors, the time to preserve the lien by
registering a claim for lien was increased from 45 days to 60 days,
and the time to perfect by commencing an action was increased from
45 days to 90 days.
But there is a significant catch in the form of the three
transition provisions in the Act.
The transition provisions say that in certain circumstances, the
old timelines will apply, even if a subcontract was entered into
after July 1, 2018.
Two of the transition provisions are based on the circumstances
surrounding the contract between the owner and the contractor (the
“contract” in the Act). The third transition provision
is based on whether the premises is subject to a leasehold
interest. If any one of the three circumstances exist, then the old
timelines apply.