There are a few tricks and traps associated with the progressive
release of builders' lien holdbacks. As mentioned in a
prior article, the Alberta Builders' Lien Act
includes provisions for releasing the statutory holdback early, or
in stages ("progressively"), which can be very important
to promote cash flow on larger construction projects. In the
simplest terms, a Certificate of Substantial Performance may be
used to authorize the release of part of the holdback – that
is, the holdback in relation to the value of work referenced in the
Certificate – even though the overall project is not yet
entirely complete.
Basic Principles
As a starting point, the Builders' Lien Act
requires the owner to retain a 10% lien holdback throughout
construction. On large projects, this can result in a significant
drag on cash flow to the contractor and subcontractors. In
particular, subcontracts often provide that payment of the
subcontractor's holdback is not due until the