Construction delay claims are notoriously complex, particularly when determining responsibility for concurrent delays. The Ontario Superior Court provided new direction for assessing concurrent...

CanadaReal Estate and Construction

Construction delay claims are notoriously complex, particularly when determining responsibility for concurrent delays. The Ontario Superior Court provided new direction for assessing concurrent delay in its January 18, 2021 decision in Schindler Elevator Corporation v. Walsh Construction Company of Canada (2021 ONSC 283).1

This case arose out of the construction of a new hospital in downtown Toronto by a partnership between Walsh Construction Company of Canada and Bondfield Construction Company Limited ("WBP") for the Women's College Hospital Capital Redevelopment Project (the "Project").   Schindler Elevator Corporation ("Schindler") was hired as the elevator subcontractor. 

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from