Many of us have heard of a construction holdback, and may have
even experienced the standard 10% deduction from outstanding
accounts in relation to the holdback. But what is the
holdback for and who does it benefit?
Pursuant to sections 18 and 23 of the Builders' Lien
Act, Owners1 are required to maintain major
and minor lien funds. The major lien fund is based on 10% of
the value of the work actually done or materials actually provided
and must be held for 45 days after either a certificate of
substantial performance2 is posted, or the contract is
complete (where no certificate of substantial performance is
issued).
The minor lien fund is based on 10% of the value of work
actually done or materials actually provided after the date a
certificate of substantial performance is issued and must be held
for 45 days after project completion. (The minor lien fund
only exists after a certificate of substantial performance is
issued).