ARTICLE · 21 JULY 2015

Interpretation Of Municipal Powers To Contract

On July 2, 2015, the Supreme Court of Canada dismissed an application for leave to appeal from a recent Ontario Court of Appeal decision in 1298417 Ontario Ltd. v. Lakeshore (Town) 2014 ONCA 802.

CanadaReal Estate and Construction

On July 2, 2015, the Supreme Court of Canada dismissed an application for leave to appeal from a recent Ontario Court of Appeal decision in 1298417 Ontario Ltd. v. Lakeshore (Town) 2014 ONCA 802.

The decision in Lakeshore highlights the principle that a person contracting with a municipality should take careful notice of the municipality's power to contract.

In this case, the Town of Lakeshore entered into an agreement with the numbered company promising to reserve sewage capacity for the company's project – St. Clair Shores Subdivision.  The clause in dispute read as follows:

"The Municipality hereby grants and approves the allocation of additional capacity in the Existing System so as to allow for full development of the St. Clair Shores Subdivision, in compliance with the existing zoning provisions for the said Subdivision. For greater certainty, said additional capacity shall be deemed to have been expressly reserved for the benefit of the St. Clair Shores