Important Issues To Consider Prior To Terminating A Construction Contract: 3065448 Manitoba Ltd. v. Bolay

A 2022 decision from the Manitoba Court of King's Bench highlights the potential consequences owners face in wrongfully removing a contractor from a project.

CanadaReal Estate and Construction

A 2022 decision from the Manitoba Court of King's Bench highlights the potential consequences owners face in wrongfully removing a contractor from a project. In 3065448 Manitoba Ltd. v. Bolay, the Court awarded the plaintiff contractor damages as a result of the defendant owner's wrongful termination of the contract - despite the owner's concerns relating to delays and deficient work on the part of the contractor.

Facts

3065448 Manitoba Ltd. (the "Contractor") and Etienne Bolay (the "Owner") entered into a contract (the "Contract") for the construction of a concrete foundation for a chicken coop (the "Project"). The Contract contained an estimated completion date for the Project.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from