In December 2021 the Canadian Construction Association released an updated version of its widely used standard form stipulated price subcontract, the CCA 1-2021: Stipulated Price Subcontract.

CanadaReal Estate and Construction

In December 2021 the Canadian Construction Association released an updated version of its widely used standard form stipulated price subcontract, the CCA 1-2021: Stipulated Price Subcontract. The updated subcontract contains several changes from its predecessor, the CCA 1-2008. Notably, the new CCA 1-2021 has been modified to align more closely with the new CCDC 2-2020 stipulated price prime contract. Below is a high level summary of some of the key changes in the new CCA 1-2021 subcontract.

If your organization uses the CCA 1 subcontract, it will want to consider migrating to the new subcontract form and updating your supplementary conditions accordingly.

Payment terms

Similar to the CCDC 2-2020, the payment terms in the new CCA 1-2021 now clarify that the Contractor's payment obligations are subject to "Payment Legislation". This would include the prompt payment rules under Ontario's Construction Act and similar prompt payment legislation that may

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from