Elite Construction Inc. v. Canada – Compliance With Contractual Notice Provisions Is A Must

Miller Thomson
Miller Thomson
Contributor

Miller Thomson

Miller Thomson LLP ("Miller Thomson") is a national business law firm with approximately 500...

View firm profile
Explore more from Miller Thomson

In large-scale construction projects, delays to the schedule of completion are almost inevitable. Often, the delays to the project will result from circumstances outside of a contractor's control...

CanadaReal Estate and Construction

In large-scale construction projects, delays to the schedule of completion are almost inevitable. Often, the delays to the project will result from circumstances outside of a contractor's control, and can impact the contractor's already tight profit margins.

As a result, contracts for large-scale construction projects have increasingly included terms permitting a contractor to submit claims for additional expenses it has incurred from delays to the project, provided that it meets certain requirements to provide the owner with notice of its intention to claim for delay. The recent decision of the Ontario Superior Court of Justice in Elite Construction Inc. v. Canada1(Elite) confirms that strict compliance with contractual notice provisions is a prerequisite to claiming damages for delay.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from