Don't Be Left Guessing On Your Estimates

The Alberta Court of Justice reaffirms basic contractual principles when analyzing estimates in Medusa Contracting Inc. v Efficient Quality Homes Inc., 2023 ABCJ 123 ("Medusa Contracting").

CanadaReal Estate and Construction

The Alberta Court of Justice reaffirms basic contractual principles when analyzing estimates in Medusa Contracting Inc. v Efficient Quality Homes Inc., 2023 ABCJ 123 ("Medusa Contracting").

Developers and homeowners are often provided estimates that may turn into the contractual basis for the work being undertaken on a project. However, when multiple estimates are provided, questions may arise as to which estimate will ultimately be relied upon.

BACKGROUND

Medusa Contracting Inc. (the "Plaintiff') was hired to complete the framing of a new home. The Plaintiff provided an estimate to Efficient Quality Homes Inc. (the "Defendant") on September 25, 2021, and quoted a price of $26,793.90 for the work (the "first estimate"). The following week, the Plaintiff presented another document: an estimate of $20,500 (the "second estimate").

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from