ARTICLE · 14 JANUARY 2026

Changes To Ontario's Construction Act Effective January 1, 2026

Borden Ladner Gervais LLP
Borden Ladner Gervais LLP
Contributor
Borden Ladner Gervais LLP

Borden Ladner Gervais LLP

With over 750 lawyers, intellectual property agents and other professionals, BLG services...

View firm profile
Explore more from Borden Ladner Gervais LLP

The most significant implication of these amendments are to the administration of the statutory holdback and the requirement for the annual release of holdback going forward for construction projects in Ontario.

CanadaReal Estate and Construction

The most recent amendments to Ontario's Construction Act are now effective (as of January 1, 2026).

The most significant implication of these amendments are to the administration of the statutory holdback and the requirement for the annual release of holdback going forward for construction projects in Ontario.

The amendments were introduced through Building Ontario for You Act (Budget Measures) (Bill 216). An overview of key amendments under Bill 216 is set out in BLG's article: Are you prepared for the new changes to Ontario's  Construction Act?

More recently, the Ontario government announced the following:

  • The Ontario government proclaimed that the amendments would come into force on January 1, 2026; but changed the original proposed process for the annual release of holdback (section 26). Most importantly, the requirement for annual lien expiry has been removed. Owners will still be required to release holdback on an annual basis; however, lien rights will not expire on an

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from