Certificate Of Substantial Performance Limits Lien Rights Even Without Posting

There was conflicting evidence if and when the CSP was posted in accordance with the requirements of the Builders' Lien Act.

CanadaReal Estate and Construction

It has always been my view that a Certificate of Substantial Performance (CSP) must be properly posted to be valid, but the Court of Appeal has recently determined otherwise.

The CSP and The Builders' Lien Act

The Builders Lien Act (BLA) of Alberta requires a lien to be registered within 45 days of completion or abandonment of the contract for which the lien is claimed (90 days in the case of an oil or gas well site), failing which it expires. But lien claimants must also be aware that there is a deadline triggered by the issuance of a CSP relating to their contract or subcontract.

45 (or 90) days after the CSP is issued, the owner may safely release the "major lien fund" (i.e. 10% of the value of the work actually done and materials actually furnished under the contract at the date of issue of the certificate of substantial performance, plus any additional amounts owing on the contract), provided no liens are registered. All that remains as security for lien

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from