It has always been my view that a Certificate of Substantial
Performance (CSP) must be properly posted to be valid, but the
Court of Appeal has recently determined otherwise.
The CSP and The Builders' Lien Act
The Builders Lien Act (BLA) of Alberta requires a lien to be
registered within 45 days of completion or abandonment of the
contract for which the lien is claimed (90 days in the case of an
oil or gas well site), failing which it expires. But lien claimants
must also be aware that there is a deadline triggered by the
issuance of a CSP relating to their contract or subcontract.
45 (or 90) days after the CSP is issued, the owner may safely
release the "major lien fund" (i.e. 10% of the value of
the work actually done and materials actually furnished under the
contract at the date of issue of the certificate of substantial
performance, plus any additional amounts owing on the contract),
provided no liens are registered. All that remains as security for
lien