Can Owners Delay Remediation Work Until Liability Is Determined?

In Murray v Windsor Brunello Ltd., 2024 ABKB 291, the Plaintiff Owners engaged the Defendant Contractor to build a home, which was constructed with significant defects.

CanadaReal Estate and Construction

In Murray v Windsor Brunello Ltd., 2024 ABKB 291, the Plaintiff Owners engaged the Defendant Contractor to build a home, which was constructed with significant defects. The Owners sued the Contractor for negligence (among other causes of action).

As of the trial date, the Owners had not undertaken any remedial work, submitting that they were waiting for the lawsuit to be resolved as the remediation would require dismantling half of the home. The Contractor took the position that the Owners' delay constituted a failure to mitigate and that damages should be reduced accordingly.

The main issue was whether the delay in remediation work was reasonable. The Court also considered when damages should be assessed and whether the Owners' claim for "escalation" (inflation) was valid.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from