In March 2015, we reported on the Province's first reading
of Bill 73 – Smart Growth for Our Communities Act,
2015 – and some of its key changes to the Planning
Act and the Development Charges Act, 1997. On July 1,
2016, a number of the Bill 73 amendments will come into force. The
following is a summary of the changes to the Planning Act which you
should look out for:
Decision and Appeal Deadlines:
Before Bill 73, an applicant for an official plan (OP) amendment
could appeal from the municipality's failure to make a decision
180 days after the application was complete. Under the changes, the
municipality or approval authority may extend that 180-day time
period by 90 days.
Parkland Dedication: The
Planning Act allows an approval authority to impose, as a condition
of approval of a residential plan of subdivision, that land be
conveyed to the municipality for park purposes or that cash-in-lieu
(CIL) be paid at the rate of 5% of the land area or an alternative
rate