On August 6, 2019, the B.C. Court of Appeal (Court) upheld the
provincial Minister of Environment's (Minister) determination
that the Jumbo Glacier Resort was not "substantially
started" by the deadline set out in its environmental
assessment certificate.
This decision will be of interest to the nearly 30 approved
projects in British Columbia which have not yet sought a
"substantially started" determination from the Minister.
The court decision confirms the Minister can focus the inquiry on
physical construction and ignore factors that delayed the project,
even when those factors are within the government's
control.
BACKGROUND
Glacier Resorts Ltd. (Glacier) is the proponent of the Jumbo
Glacier Resort project (Project), a large year-round ski resort
intended to be developed in the East Kootenay region of British
Columbia, between Invermere and Nelson. The Project was first
proposed in 1991, but has a long and drawn out history.